Scope: Build an underground electrical duct bank from the Forge Street Substation to the location of the new Student Recreation Center. This reduces the load of the Carroll Street Substation and provides alternate feeds for existing buildings and feeds for new buildings on the proposed route. Status: Construction start: May 2002. Construction complete: December 2002. Engineer: Scheeser Buckley Mayfield, Inc., Uniontown, Ohio Last update: 09/15/2004
|
||