Scope:

Tear off and replace existing Single Ply Roofing System (EPDM) and install .060 reinforced EPDM fully adhered system.

Status:

Architectural metal installation ongoing. Lightning rod installed.

Construction start 05/2006. Construction complete spring 2007.

Construction 95% complete.

Design: TC Architects, Akron, Ohio

Last update: 01/24/2007