PFOC Chiller Replacements


Scope:

Add one new chiller and replace two existing chillers to increase cooling capacity. Add one cell to one of the three cooling towers.

Status:

Phase I construction 100% complete. Closeout in progress.

Chiller to replace existing units #4 and #5 ordered.

Preliminary construction work to begin 12/04/2006.

Construction start 04/2006. Construction complete 04/2007.

Design: Fosdick and Hilmer, Cincinnati, Ohio

Last update: 01/24/2007