SCHRANK HALL RENOVATION

Description: Total replacement of plumbing systems in Schrank Hall South including mechanical room improvements. Roof replacements of Schrank Hall North and South, including removal of abandoned cooling tower. Plaza and parking deck renovations. Electrical distribution improvements. ADA elevator modifications. Oil switch replacement. Fire alarm replacement. Asbestos abatement of materials in Schrank Hall North and South.

Location: 240 Carroll St.

Construction Start: December 2002

Project Complete: January 2004

Project Budget: $6,138,393

Architect: Hasenstab Architects, Inc., Akron, Ohio

Construction Manager: Ozanne Construction Company Inc., Cleveland, Ohio

 