STUDENT
UNION BUILDING
Description:
Designs include: a food court; large assembly rooms; conference/meeting
rooms; recreational space for bowling, billiards and game
room; retail space for bookstore, bank and post office;
computer labs; lounge area; student organization office
space; and administrative office space. During Phase I of
the project, a new wing was constructed at the west end
of the existing student center. In the second phase, the
existing center was demolished and a new wing built on that
site.
Location:
303 Carroll Street
Size:
198,000 square feet
Construction
Start: July 2001
Phase
I complete: December 2002
Gardner
Demolition Start: December 2002
Gardner
Demolition Complete: March 2003
Phase
II Start: March 2003
Construction
Complete: August 2004
Project
Budget: $41,100,000
Architect:
WTW Architects, Cleveland, Ohio
Construction
Manager: The Ruhlin/Kenmore Joint Venture, Akron, Ohio